Probability distribution fitting of schedule overruns in construction projects

P. E D Love, C. P. Sing, X. Wang, D. J. Edwards, H. Odeyinka

Research output: Journal Publications and ReviewsRGC 21 - Publication in refereed journalpeer-review

Abstract

The probability of schedule overruns for construction and engineering projects can be ascertained using a 'best fit' probability distribution from an empirical distribution. The statistical characteristics of schedule overruns occurring in 276 Australian construction and engineering projects were analysed. Skewness and kurtosis values revealed that schedule overruns are non-Gaussian. Theoretical probability distributions were then fitted to the schedule overrun data; including the Kolmogorov-Smirnov, Anderson-Darling and Chi-Squared non-parametric tests to determine the 'Goodness of Fit'. A Four Parameter Burr probability function best described the behaviour of schedule overruns, provided the best overall distribution fit and was used to calculate the probability of a schedule overrun being experienced. The statistical characteristics of contract size and schedule overruns were also analysed, and the Wakeby (AU$101 m) models provided the best distribution fits and were used to calculate schedule overrun probabilities by contract size. © 2013 Operational Research Society Ltd.
Original languageEnglish
Pages (from-to)1231-1247
JournalJournal of the Operational Research Society
Volume64
Issue number8
DOIs
Publication statusPublished - Aug 2013
Externally publishedYes

Research Keywords

  • Australia
  • distribution fitting
  • probability
  • probability distribution
  • schedule overrun