A practical approach to scheduling a multistage, multiprocessor flow-shop problem

Research output: Journal Publications and ReviewsRGC 21 - Publication in refereed journalpeer-review

Abstract

This paper describes a rubber manufacturing system and the numerous technological, operating and quality constraints governing its scheduling process. The complex system resembles a flow-shop problem where all jobs share the same general processing order on a progression of machines. The manufacturing system is defined in terms of production stages and parallel processing lines. One stage can process two or more jobs simultaneously. Jobs are often split on the last stage so that two or more parallel processing lines process the same job simultaneously. The scheduling for such a multistage, multiprocessor flow shop is dominated by the quality constraints. A pragmatic approach is provided in which a schedule is constructed through extensive iterations of analysis and simulation. © 1989 Taylor & Francis Group, LLC.
Original languageEnglish
Pages (from-to)1733-1742
JournalInternational Journal of Production Research
Volume27
Issue number10
DOIs
Publication statusPublished - Oct 1989
Externally publishedYes

UN SDGs

This output contributes to the following UN Sustainable Development Goals (SDGs)

  1. SDG 9 - Industry, Innovation, and Infrastructure
    SDG 9 Industry, Innovation, and Infrastructure

Fingerprint

Dive into the research topics of 'A practical approach to scheduling a multistage, multiprocessor flow-shop problem'. Together they form a unique fingerprint.

Cite this