深圳平安金融中心施工模拟研究

Translated title of the contribution: Construction sequence analysis of Shenzhen Pingan financial center
  • 李秋胜*
  • , 汪辉
  • *Corresponding author for this work

Research output: Journal Publications and ReviewsRGC 22 - Publication in policy or professional journal

Abstract

In high-rise buildings, construction process and non-load effect are not considered in conventional finite element analysis. In this paper, for the construction project of Shenzhen Pingan Financial Center (PAFC), which is the highest tall building under construction in China, full construction process simulation was conducted by dividing the structure into 25 construction stages using Midas/Gen software. Vertical cumulative deformations of the concrete core-wall and mega columns, and the deformation variance due to the shrinkage and creep of concrete were studied. The simulation results show that vertical deformation caused by the shrinkage and creep causes more than half of the total deformation, and the effect of the shrinkage and creep cannot be ignored. In addition, the internal forces of the critical members in the building structure including belt trusses, outriggers, mega diagonal brace, and V-typed brace during construction were also investigated. The different loading conditions were applied to the structural members at different locations. The stress of cord members in the trusses changes little, while the stress of web members in the trusses changes significantly during the construction process, which indicates that the design of the structure members can be varied with the loading conditions. In the final construction stage, the stress of the structure members is less than the material strength with a certain safety margin, and the measurement data can be used as reference for actual construction.
Translated title of the contributionConstruction sequence analysis of Shenzhen Pingan financial center
Original languageChinese (Simplified)
Pages (from-to)97-105
Journal湖南大学学报(自然科学版)
Volume43
Issue number5
DOIs
Publication statusPublished - 25 May 2016

Research Keywords

  • 超高层建筑
  • 施工模拟
  • 收缩徐变
  • 竖向变形
  • Super high-rise building
  • Construction sequence
  • Shrinkage and creep
  • Vertical deformation of structural member